We use cookies to ensure that we give you the best experience on our website. If you click 'Accept all cookies' we'll assume that you are happy to receive all cookies and you won't see this message again. If you click 'Reject all non-essential cookies' only necessary cookies providing core functionality such as security, network management, and accessibility will be enabled. Click 'Find out more' for information on how to change your cookie settings.

Piling work starts

  • The pedestrian route is now fully operational
  • Deliveries will be increasing over the coming weeks, as works progress
  • Please take care and plan your journey accordingly. Site maps are located at the four main entrances to the Science Area
  • Preparation for piling is progressing well (piling rig is expected on site Tuesday 27 November). Piling work is expected to last 12 weeks (see Building Sequence Look Ahead)
  • A small office, providing welfare facilities for site workers, has been set up on the North of the site, outside the Sherrington Building

 

The Building Sequence Look Ahead shows you what to expect on site over the coming weeks

Further information can be found in Newsletter Issue 2, Nov 2018