March 2019 - Capping beam complete, excavation starts
- Capping beam is now complete
- Excavation to the basement is under way. Expect 80 - 90 wagons on site each day, removing dirt from the area. Take care and please used pedestrian routes
- There will be less noisy work in the short term, and Science Area users will be informed if this changes
- A temporary structure is to be built on edge of University Parks to house essential welfare facilities. Read more
Further information can be found in Newsletter Issue 4, March 2019