Old Road Campus Latest Updates
Last updated: 12th June 2026
progress and Look ahead
Plot B1
Current activities
- Internal fit out
- External cladding and ground works
- The area highlighted in red below remains fenced off. The work to develop this route into a formal pathway is scheduled for completion July 2026
Please use alternative access points as shown in yellow.

-
The vegetation clearance has been undertaken in accordance with mitigation measures instructed by the ecology consultant to ensure minimal impact to wildlife and the environment.
Future activities
- Removal of Morgan Sindall cabins adjacent to Boundary Brook House via crane lift. Scheduled mid July. Further details will be provided shortly
- Furniture deliveries with associated increase of large vehicle movements expected from mid-June onwards
- Please be mindful of large vehicle movements during these activities
Road closure between plot b1 and ndmrb
- The closure will be in operation from Saturday 7th February 2026 until further notice (estimated end June 2026)
- This is to facilitate the storage of materials and preparation for future ground works required for the completion of the B1 development. The closure area is indicated in red shaded area below.

- There will be no vehicle, pedestrian or cycle access through this area during the closure period.
- The closure and traffic diversions will be clearly signposted and vehicle access managed with Traffic Marshalls / Banks persons.
- The traffic management plan below provides more detail of vehicle routes and closure points.

-
Access to Triangle Nursery is retained
-
BOC deliveries to CHG and hazardous waste collections will be facilitated as required
-
Access to NDMRB goods in via roller shutter / Nitrogen deliveries will be facilitated as required
Should you have any queries regarding access through this area during the closure please contact:
Alex Mitchell, Morgan Sindall Site Manager: 07345 469046
Plot B2
Current activities
- lattice work commenced. Concrete pouring continues. Scheduled completion Mid-July
- Current activities are expected to result in minimal noise and vibration. Mitigations and monitoring remain in place
-
Please be aware of frequent large vehicle movements from the site linked to this activity
Future activities
-
Installation of 2nd tower crane. Methodology will be as per the previous crane erection, with all activities being contained within the site boundary. Currently scheduled for weekend of 14th - 15th June 2026 (weather permitting).
Cycle parking - Triangle nursery
- The cycle bays located as outlined in green below are allocated for staff and parents/carers of Triangle nursery only. Your support with this is appreciated.

nursery path
- The path adjacent to the Triangle nursery remains restricted to pedestrians only throughout the duration of Plot B2 works. A fencing chicane system has been installed to encourage cyclists to dismount and push bikes along this pathway.
- Cyclists must dismount along this path for the safety of all path users. Thank you for your support with this.
- Access to the campus from the South is unaffected.