We use cookies to ensure that we give you the best experience on our website. If you click 'Accept all cookies' we'll assume that you are happy to receive all cookies and you won't see this message again. If you click 'Reject all non-essential cookies' only necessary cookies providing core functionality such as security, network management, and accessibility will be enabled. Click 'Find out more' for information on how to change your cookie settings.

Last updated: 21st January 2026

progress and Look ahead  

Plot B1 

Current activities 
  • Internal - Fit out, partition walling, first fix M&E 
  • External – drainage, utilities connections 
  • Preparatory works to clear low level vegetation in area highlighted below in red.

Image showing location of vegetation clearance between Plot B1 and Old Road

  • This is an informal route through the wooded area. Work to develop this route into a formal pathway with improved surface will commence in March 2026.
    The cleared area will be fenced off until the main works start.

Plot B2

Current activities 
  • Secant piling continues. 
    The current piling is focused in the areas shown in green below. This area is scheduled for completion on 2nd February.
    Focus will then move to the areas marked in orange, with completion schedule by end March
Secant piling locations.png
  • Mitigations are in place however this activity creates intermittent vibration and persistent loud noise. This continues to be monitored to ensure safe levels are maintained.
  • We appreciate the disruption this may cause, the project team endeavour to minimise this wherever possible within project constraints 
         Please be aware of frequent large vehicle movements from the site linked to this activity.
  • Temporary closure of IDRM access road. Saturday 24th January
    The access road will be closed to allow excavation works to take place in area shown in yellow below.
    Vehicle access during this period will be permitted under control of a banksman using road plates.
Image to show location of IDRM access road closure
  • From Sunday onwards, road plates will be installed so the area can remain open.
    Concrete will be poured on Monday 26th January, during which there will be a short period of approximately 20 minutes where access may be briefly managed, but the road will not be closed. 

Future activities

  • Occasional closures of footpath to rear of BBH – Dates TBC but notice will be provided. Laing O'Rourke aim to avoid busy periods
  • Access gate (3) to be created on IDRM access road. Minimal anticipated impact to campus
  • Accessibility / lift access to be created at cabins by BBH. May require temporary footpath restriction. Laing O'Rourke aim to avoid busy periods for these works

Cycle parking - Triangle nursery

The cycle bays located as outlined in green below are allocated for staff and parents of Triangle nursery only. Your support with this is appreciated.
Image showing location of cycle bay opposite Triangle nursery, adjacent to Big Data Institute

nursery path

The path adjacent to the Triangle nursery remains restricted to pedestrians only throughout the duration of Plot B2 works. A fencing chicane system has been installed to encourage cyclists to dismount and push bikes along this pathway. 

Cyclists must dismount along this path for the safety of all path users. Thank you for your support with this. 

Access to the campus from the South is unaffected.Image to show location of path alongside Triangle nursery which is restricted to pedestrians only