Old Road Campus Latest Updates
Last updated: 29th October 2025
progress and Look ahead
plot b2 sheet piling works
This work has commenced and will continue as scheduled below:
-
Tuesday 28 October - Saturday 1 November 2025 inclusive
-
Monday 3 November - Tuesday 4 November 2025 inclusive
This activity is likely to generate noticeable noise and vibration.
The project team has worked hard to minimise the amount of piling required for the development and work with the contractor to take all reasonable steps to manage noise and vibrations to minimise the impact to campus of these necessary works.
We will advise as soon as possible should there be any amendments to this scheduling. Any queries please contact projects@medsci.ox.ac.uk
idrm access road diversion

Cycle parking - Triangle nursery

nursery path
The path adjacent to the Triangle nursery remains restricted to pedestrians only throughout the duration of Plot B2 works. A fencing chicane system has been installed to encourage cyclists to dismount and push bikes along this pathway.
Cyclists must dismount along this path for the safety of all path users. Thank you for your support with this.
Access to the campus from the South is unaffected.
