Cookies on this website

We use cookies to ensure that we give you the best experience on our website. If you click 'Accept all cookies' we'll assume that you are happy to receive all cookies and you won't see this message again. If you click 'Reject all non-essential cookies' only necessary cookies providing core functionality such as security, network management, and accessibility will be enabled. Click 'Find out more' for information on how to change your cookie settings.

Last updated: 22nd July 2026

progress and Look ahead  

Plot B1 

The construction of the building is now completed and final exterior and interior activities are underway.

Current activities 

  • Final ground works and interior fixtures
  • Furniture deliveries with associated increase of large vehicle movements
  • * Please be mindful of large vehicle movements during these activities *
  • The area highlighted in red below remains fenced off. The work to develop this route into a formal pathway is scheduled for completion July 2026
    Please use alternative access points as shown in yellow.

 Image to show location of woodland path closure and alternative access from Old Road

  • The vegetation clearance has been undertaken in accordance with mitigation measures instructed by the ecology consultant to ensure minimal impact to wildlife and the environment.

Future activities

  • Removal of Morgan Sindall cabins adjacent to Boundary Brook House via crane lift. Scheduled Saturday 1st and Sunday 2nd of August. These activities are not expected to cause significant disruption.

Road closure between plot b1 and ndmrb 

  • The closure will be in operation from Saturday 7th February 2026 until further notice 
  • This is to facilitate the storage of materials and preparation for future ground works required for the completion of the B1 development. The closure area is indicated in red shaded area below. 
Image to show location of closure of road between B1 plot and NDMRB
  • There will be no vehicle, pedestrian or cycle access through this area during the closure period.
  • The closure and traffic diversions will be clearly signposted and vehicle access managed with Traffic Marshalls / Banks persons. 
  • The traffic management plan below provides more detail of vehicle routes and closure points.
Traffic Management plan for road closure between B1 site and NDMRB Building
Please note
  • Access to Triangle Nursery is retained

  • BOC deliveries to CHG and hazardous waste collections will be facilitated as required

  • Access to NDMRB goods in via roller shutter / Nitrogen deliveries will be facilitated as required

Should you have any queries regarding access through this area during the closure please contact: 

Alex Mitchell, Morgan Sindall Site Manager: 07345 469046

Plot B2

Current activities 

  • 2nd tower crane installed and operational
  • Concrete pouring continues. Scheduled completion Mid-July
  • Main structural framework build has commenced
  • Current activities are expected to result in minimal noise and vibration. Mitigations and monitoring remain in place
*Please be aware of frequent large vehicle movements to and from the site*

Cycle parking - Triangle nursery

  • The cycle bays located as outlined in green below are allocated for staff and parents/carers of Triangle nursery only. Your support with this is appreciated.
Image showing location of cycle bay opposite Triangle nursery, adjacent to Big Data Institute

nursery path

  • The path adjacent to the Triangle nursery remains restricted to pedestrians only throughout the duration of Plot B2 works. A fencing chicane system has been installed to encourage cyclists to dismount and push bikes along this pathway. 
  • Cyclists must dismount along this path for the safety of all path users. Thank you for your support with this. 
  • Access to the campus from the South is unaffected.