Old Road Campus Latest Updates
Last updated: 27th January 2026
progress and Look ahead
Plot B1
-
Internal - Fit out, partition walling, first fix M&E
-
External – drainage, utilities connections
-
There is currently no access to ORC from Old Road via the woodland path due to preparatory works for pathway improvements. This area is indicated in red on the image belowPlease use alternative access points as shown in yellow.

-
Work to develop this route into a formal pathway with improved surface will commence in March 2026.The cleared area will be fenced off until the main works start.
Plot B2
-
Secant piling continues.The current piling is focused in the areas shown in green below. This area is scheduled for completion on 2nd February.Focus will then move to the areas marked in orange, with completion schedule by end March
-
Mitigations are in place however this activity creates intermittent vibration and persistent loud noise. This continues to be monitored to ensure safe levels are maintained.
-
We appreciate the disruption this may cause, the project team endeavour to minimise this wherever possible within project constraints
Future activities
-
Occasional closures of footpath to rear of BBH – Dates TBC but notice will be provided. Laing O'Rourke aim to avoid busy periods
-
Access gate (3) to be created on IDRM access road. Minimal anticipated impact to campus
-
Accessibility / lift access to be created at cabins by BBH. May require temporary footpath restriction. Laing O'Rourke aim to avoid busy periods for these works
Cycle parking - Triangle nursery

nursery path
The path adjacent to the Triangle nursery remains restricted to pedestrians only throughout the duration of Plot B2 works. A fencing chicane system has been installed to encourage cyclists to dismount and push bikes along this pathway.
Cyclists must dismount along this path for the safety of all path users. Thank you for your support with this.
Access to the campus from the South is unaffected.
